HOW TO MANAGE CONSTRUCTION DISPUTES TO MINIMIZE SURETY
AND CONSTRUCTION CLAIMS. PART 3: FORCE
MAJEURE CLAIMS.
Construction is a
business fraught with risk. Disputes
over even the smallest of issues can quickly escalate, with crippling consequences
to the project and the parties. Over the
years, the construction industry has developed various methods of contractually
allocating the risk of project delay and disruption. Some of these methods include liquidated
damages provisions, "no damages for delay" clauses, mutual waivers of
consequential damages, provisions that limit liability, claims notice
provisions, and provisions addressing responsibility for the adequacy of the
construction plans and specifications. Parties frequently litigate the sufficiency of
these risk-shifting efforts in conjunction with the underlying merits of delay
and disruption disputes.
Construction Claims & Disputes
In Part I of our
series of how to manage construction disputes to minimize surety and
construction claims, we addressed the construction delay claims and the methods
typically used to analyze them.
We indicated there
that the most frequently encountered claims include:
1.
Construction
Delay Claims
2.
Disruption
and Loss of Labor Productivity Claims
3.
Design
and Construction Defect Claims
4.
Force
Majeure Claims
5.
Acceleration
or Compression of the Schedule Claims
6.
Suspension,
Termination and Default Claims
7.
Differing
Site Conditions Claims
8.
Change
Order and Extra Work Claims
9.
Cost
Overrun Claims
10.
Unacceptable
Workmanship or Substituted Material Claims
11.
Non-payment
Claims (stop notice (or Notice to Withhold) claims, mechanics’ lien (only for
private construction projects) and payment bond claims)
Part III of this
series discusses item 4 above: Force Majeure Claims
Third Party / Force
Majeure
Those
engaged in construction or other closely related fields know that the wording
of a contract can make or break your entire business. Some contractors will create their own
agreements to bind themselves and clients together while some will utilize a
standard industry form contract purchased from a third party. Either of the
scenarios can yield unfavorable results if due care isn't taken in ensuring
that certain clauses are included and are written correctly.
When
contractors and other construction professionals hear "force
majeure," many think of an "act of god" or visions of lightning
strikes or an earthquake. But force majeure can mean so much more. A
well-drafted contract or agreement will define exactly what a force majeure is
and what will happen if such circumstances arise.
The direct
translation of force majeure is “greater force”, or in other words a force that
is out of the hands of any party to the contract. Typically, these clauses are inserted into
contracts to excuse a party from liability if an event which could not be
foreseen prevents that party from fulfilling its contractual obligations. See
Pacific Vegetable Oil Corp. v. C.S.T., Ltd. (1991)
29 Cal.2d 228). Examples of typical
force majeure events include natural disasters, insurrections, war or “Acts of
God”. The Supreme Court of the United
States has indicated that a force majeure event is one that is “…unexpected,
something beyond reasonable foresight and skill.”
Force Majeure are
those unforeseen events with causes beyond the contractor’s control, for which
the contractor is deemed excusable in their failure to perform within the
required time limits. Force Majeure
schedule impacts are commonly known as unforeseen events, causes beyond the
contractor’s control, and events without fault or negligence. Contracting Common examples of delays that are
beyond the control and without the fault of the contractor include but are not
limited to:
•Acts
of God or of the public enemy
•Acts
of the Government in either its sovereign or contractual capacity
•Fires
• Epidemics
• Quarantine
restrictions
• Strikes
• Freight
embargoes
• Unusually severe weather. See Wickwire, J.M., T.J. Driscoll, S.B.
Hurlbut , and S. B. Hillman (2003), “Construction Scheduling: Preparation,
Liability, and Claims, Construction Library Law”, 2nd ed., Aspen Publishers,
USA.
Under such
provisions, the contractor is entitled
to an extension of time to complete work if the delay is deemed excusable.
An Act of God typically refers to
a natural occurrence caused directly and exclusively by natural forces without
any human intervention, which could not have been reasonably foreseen or
prevented by the contractor or any other party to the contract. This category includes earthquakes,
landslides, tornadoes, hurricanes, lightning, and floods. Liquidated damages are not to be assessed
during this extended performance period, provided the delay is not directly or
indirectly the fault of the contractor.
Abnormal weather
conditions can greatly influence the execution of activities, in turn affecting
completion of the project on time. Most
contract documents state that the only weather that should impact the
completion of the project within schedule is “unusually severe” weather
conditions. Weather can have both a direct and indirect impact on construction.
For example, if unusually severe rainfall amounts stop all earthwork
activities, there is a direct effect and stoppage of work. In addition to the days that the rain has
taken place, the indirect effect of the rain is that the earthwork activity cannot
be started until the soil has dropped to a workable moisture content.
Not
all unexpected events or conditions, however, are situations that will excuse
performance of a contractual obligation.
To obtain relief under the force majeure clause the
contractor must generally clear three hurdles: First, something unexpected must
occur. Second, the risk of the unexpected occurrence must not have been
allocated to either party by the agreement.
Finally, the unexpected occurrence must render performance commercially
impracticable. If a contractor fails to
protect itself from a foreseeable contingency, it has assumed that risk. Furthermore, a contractor is expected to take
measures to prevent the harmful effects of uncontrollable events whenever
reasonable - known as "mitigation." Reasonable weather
protection measures should be employed even if the contractor has no notice of
a "freak" storm brewing.
If no Force Majeure
Clause, then the Contractor bears the Risk
When
there is no force majeure clause in the contract, the risk of loss
for any unexpected or unforeseen event generally falls on the contractor. Since force majeure events are
generally acts of nature (or God), it is said "because the same rain falls
on the owner's head as on the contractor's" both parties share the risk;
therefore, the contractor is entitled to a time extension, but not
compensation. Therefore, if the event
causes a delay in performance, a contractor could be allowed to raise the
doctrine of force majeure to obtain an extension of time
without penalty and as a defense against assessment of liquidated damages.
Nevertheless, the contractor will not normally be permitted to recover
losses or damages resulting from that delay. Moreover, contractors
typically bear the costs to demobilize and remobilize, or repair work caused by
an "Act of God" event.
It
is not uncommon, therefore, for parties to include a force majeure clause
in their contracts to limit the risk that a future event will prevent them from
performing and subject them to liability. Force majeure provisions
serve two purposes: allocating risk and providing notice to the parties of
events that may suspend or excuse performance. If an event that triggers
a force majeure clause occurs, theoretically, the burden will
be borne by the party that assumed the risk.
Parties seeking to limit their exposure to
a force majeure event should be careful, however, to use
specific and detailed language in defining the scope and effect of a force
majeure clause. Sun Operating Ltd. P’ship v. Holt, 984 S.W.2d 277, 283
(Tex. App. Amarillo 1998, pet. denied); see
also Maralex Res., Inc. v. Gilbreath, 76
P.3d 626, 636 (N.M. 2003); R&B Falcon Drilling Co. v. Am. Exploration Co.,
154 F. Supp. 2d 969, 973 (S.D. Tex. 2000).
The
traditional boilerplate language contained in most force majeure clauses
is too general and vague for modern circumstances because courts tend to
narrowly interpret such language and limit its application to the events
specifically listed.
Even if a force majeure clause properly and
adequately describes the types of incidents that are covered by the clause,
problems could still exist if the clause is not completely clear. For example, if a contractor is laying a
building's foundation, and a flood would be considered a force majeure, if a flood
occurs, what is the course of action for the contractor to take? And what happens to his contract? Does it
terminate, or does the contractor have the ability to continue work? If additional work is needed how much
compensation is due to the contractor? These
provisions should also address important questions, such as: What are all the events
or conditions that are considered force majeure? Who is allowed to invoke the clause? What is the appropriate remedy where the clause
is invoked? Which contractual obligations are covered by the clause?
How should the parties determine whether the event creates an inability
to perform?
A properly written force majeure clause
will address these questions and more to protect the contractor from exposure
to unexpected liability.
Much
of the jurisprudence surrounding the interpretation of force majeure clauses
is rooted in the cases addressing the doctrines of impossibility and commercial
impracticability (including Section 2-615 of the U.C.C.). More importantly, these doctrines often set
the default rules around which the parties to a contract may bargain for more
or less protection. In dispute
resolution, courts evaluate weather delays on a case-by-case basis, considering
such factors as the job site’s geographic location, the nature of the work performed,
the contractor’s previous experience in the area, and the contractor’s reasonable
anticipation of weather conditions [Wickwire et al. 2003]. Anticipating weather can be done by looking at
historical data for typical “rain days” in the same geographic location,
accounting not only for the time of year, but also for that specific location.
Weather impacts are
not strictly limited to rain and the rainy season; also included but not
limited to abnormal humidity, frozen earth, winter weather, extreme heat, severe
weather outbreaks, wind, and hurricanes.
See Bramble,
B.B. and Callahan, M.T. Construction
Delay Claims. Third Edition. New York: Construction Law Library, Aspen
Publishers, 2000; Bramble, B.B., D’Onofrio, M.F., and Stetson, J.B. Avoiding
& Resolving Construction Claims. Kingston, Massachusetts: R.S. Means Co.,
1990.
What is not a force majeure?
Often, if a contract
defines force majeure events, unless language expands that list by stating
“including without limitation,” then an event not specified in the clause may
not excuse nonperformance. For example,
if the contract defines force majeure as a flood or hurricane, then a lightning
strike may not excuse nonperformance unless a phrase such as “including without
limitation” is in the force majeure clause.
Most force majeure clauses only provide relief in the form
of an extension of time without penalty or without assessment of liquidated
damages for a period equal to the force majeure. Clauses seldom provide any compensation
for the costs to demobilize and remobilize; to repair work; for the escalation
of material and labor prices; or the premium demanded by transporters still operating
in the affected areas. However, the contractor should review the changes or claims
clause to see if it may still be able to recoup costs.
The majority of
jurisdictions hold that a force majeure event discharges the party’s performance
even if there is no force majeure clause because the party did not assume the risk
of performance under any and all circumstances. A minority of jurisdictions
hold that, in the absence of a force majeure clause, the party prevented from
performing will be held liable for nonperformance consistent with the terms of
the contract addressing default or nonperformance
Classifying
Schedule Impacts
Once recognized
that an event has occurred in the as-built completion of a project that differs
from the established schedule of record, which potentially has an impact on the
schedule and is attributable to a party, the next step is to classify the
delay, so that a schedule impact technique can be applied. Delays are
classified into one of the following four categories:
1. Excusable,
Non-Compensable Delays
2. Excusable,
Compensable Delays
3. Non-Excusable,
Non-Compensable Delays
4. Non-Excusable,
Compensable Delays
Identifying the
category of each delay is essential before applying a schedule impact analysis
technique. Each of these four categories
is attributable to the owner, contractor, or third party / force majeure , and
will be explained in further detail.
In the northern
part of the United States, the start of spring after a long cold winter is
traditionally a welcome event. However, in recent years, the start of
spring has become synonymous with another, less welcome event: flood season.
This spring,
several areas of the United States are dealing with record high water levels
and many areas of the Province have faced difficulties with flooding.
For the
construction industry, flooding and other adverse weather events may have
severe impacts on project schedules and costs. If you’re faced with a
situation where your work will be impacted by causes outside of your control,
you will want to consult the force majeure provisions in your contract.
Aside from being an
occurrence which is truly unforeseen, a force majeure event must be of such
significance that the failure to perform in accordance with the contract could
not be overcome by the reasonable efforts of the party claiming relief.
The essential
purpose of the force majeure clause is to allocate the risk for unexpected events
between the owner and contractor (or contractor and sub-contractor or
supplier). Generally speaking, an owner
will want a tightly worded force majeure clause which limits the events
considered to be force majeure to specifically enumerated events like natural
disasters and wars. On the other hand, a
contractor will generally be looking for a more inclusive (or loosely worded)
clause which would leave the definition of force majeure open to other events,
including the failure of third parties to perform services or supply materials.
Apart from the
issue of agreeing as to what constitutes a force majeure event, parties to a
contract should also ensure that their agreement includes specific provisions
on what happens if a force majeure event occurs. Is the contractor entitled to an extension of
time and additional costs? Just an
extension of time - or just additional costs? If an extension of time and/or additional
costs are to be awarded, do the parties use a change order procedure or is
there a separate procedure to account for these claims? Are there
specific notice requirements for a party advancing a force majeure claim?
All of these questions should be answered in a good force majeure clause.
Parties should be
aware that even where a force majeure event occurs, parties are not released
from their obligations completely - they remain under a positive duty to take
reasonable steps to mitigate the damage caused by the event.
So if you find
yourself on the wrong side of Mother Nature, fires, epidemics, embargos and so
on and need guidance as to whether you’ve got a valid claim for additional time
and/or costs, look to the force majeure provisions of your contract.
ASSISTANCE IN DEVELOPING A CONSTRUCTION CLAIM
Metropolitan
provides valuable guidance in developing, analyzing, defending, and negotiating
construction claims. In the highly
competitive engineering and construction industry, construction claims
management has become an increasingly integral element to maintaining project
profitability. Our construction experts
have successfully resolved a broad range of construction claims on a variety of
projects located throughout the United States and internationally.
Although
there are many programs available on the legal aspects of construction claims,
few of these focus sufficiently on the practical aspects of claim entitlement,
documentation, preparation, analysis, and negotiation. .
Successful
assertion of a construction claim depends on first establishing entitlement,
then properly pricing the claim by assessing both direct and indirect costs.
Our
construction experts guide and assist our clients in identifying and developing
a basic claim "theme" that is consistent with the contract, the facts
and established construction practices.
The
experts at Metropolitan Forensics will:
·
provide
leadership and support by analyzing contract requirements
·
provide
assistance in assessing actual costs, project delays, and impacts when
reviewing a claim
·
help
identify and develop necessary documentation and data on the project to
accurately express the client's claim "theme"
·
provide
guidance in assessing claim options and counterclaims
·
assist
clients in calculating the costs incurred by pursuing a claim
·
prepare
claim text and exhibits and provide continuing support
ASSISTANCE IN CONSTRUCTION CLAIMS ANALYSIS
Metropolitan
project review and construction claims analysis will provide an objective,
independent appraisal of the strengths and weaknesses of a construction claim.
Our
construction experts provide clients with significant insight as to their
potential liability and accordingly, a recommended course of action. We help
clients develop and implement effective strategies for either asserting or
defending construction claims.
NEGOTIATING AND RESOLVING A CONSTRUCTION CLAIM
Metropolitan
provides valuable guidance in the negotiation of construction claims so that
clients may avoid costly litigation and still obtain an equitable claim
settlement.
·
Our
construction experts proven negotiation techniques facilitate active pursuit of
the claim without creating excessive adversary positions
·
We
assist in the development and pursuit of successful claim negotiating
strategies
·
We
lead claim negotiations as authorized by our clients and participate in
settlement negotiations on behalf of our clients
Metropolitan Engineering, Consulting & Forensics (MECF)
Providing
Competent, Expert and Objective Investigative Engineering and Consulting
Services
P.O. Box 520
Tenafly, NJ 07670-0520
Tel.: (973) 897-8162
Fax: (973) 810-0440
E-mail:
metroforensics@gmail.com
Web pages:
https://sites.google.com/site/metropolitanforensics/
https://sites.google.com/site/metropolitanenvironmental/
https://sites.google.com/site/metroforensics3/
http://metroforensics.blogspot.com/
We are happy to announce the launch of our twitter account. Please make
sure to follow us at @MetropForensics or @metroforensics
Metropolitan
appreciates your business.
Feel free to
recommend our services to your friends and colleagues.
To unsubscribe from future technical blogs and announcements, please
reply to this email with the word “unsubscribe” in the subject line.