MEC&F Expert Engineers

Thursday, January 22, 2015

TAMPA, FLORIDA-BASED ENGINEERING AND CONSTRUCTION FIRM PBSJ CORPORATION AGREED THURSDAY TO PAY $3.4 MILLION FOR VIOLATING THE FOREIGN CORRUPT PRACTICES ACT BY PAYING BRIBES AND EMPLOYING FOREIGN OFFICIALS TO WIN QATARI GOVERNMENT CONTRACTS.

TAMPA, FLORIDA-BASED ENGINEERING AND CONSTRUCTION FIRM PBSJ CORPORATION AGREED THURSDAY TO PAY $3.4 MILLION FOR VIOLATING THE FOREIGN CORRUPT PRACTICES ACT BY PAYING BRIBES AND EMPLOYING FOREIGN OFFICIALS TO WIN QATARI GOVERNMENT CONTRACTS.


Tampa, Florida-based engineering and construction firm PBSJ Corporation agreed Thursday to pay $3.4 million for violating the Foreign Corrupt Practices Act by paying bribes and employing foreign officials to win Qatari government contracts. 

PBSJ is now known as Atkins North America Holdings Corporation and no longer offers public stock in the U.S.

UK-based Atkins acquired PBSJ in 2010. The group has 17,000 employees world wide.
The SEC charged Walid Hatoum, a former international marketing director for PBSJ, with violating the FCPA's anti-bribery, internal accounting controls, and books and records provisions, and with false records offenses.

Without admitting or denying the findings, Hatoum agreed to pay a penalty of $50,000.
The SEC didn't go to court. It entered an administrative order against Hatoum. And it used a deferred prosecution agreement to resolve PBSJ's offenses. The DPA has a two-year term.
Kara Brockmeyer, chief of the SEC's FCPA unit, said: “Hatoum offered and authorized nearly $1.4 million in bribes disguised as ‘agency fees’ intended for a foreign official who used an alias to communicate confidential information that assisted PBSJ.”

The foreign official gave Hatoum and PBSJ’s international subsidiary access to "confidential sealed-bid and pricing information," the SEC said. The information helped the PBSJ subsidiary win bids in 2009 for a hotel resort development in Morocco and a light rail transit project in Qatar.

Brockmeyer said PBSJ ignored "multiple red flags that should have enabled other officers and employees to uncover the bribery scheme at an earlier stage."

Once PBSL discovered the offenses, Brokmeyer said, it self-reported them and "cooperated substantially.”
The SEC also alleged that Hatoum offered a job to a second foreign official in return for help after PBSJ lost the Morocco hotel project.

In the deferred prosecution agreement, PBSJ agreed to disgorge $2.8 million with interest of $140,000, and pay a penalty of $375,000.

"Even though the bribes themselves were not consummated before the scheme was uncovered by the company, PBSJ earned approximately $2.9 million in illicit profits because it continued work on the [Qatar] light rail project until a replacement company could be found," the SEC said.

The SEC said: "PBSJ took quick steps to end the misconduct after self-reporting to the SEC, and the company voluntarily made witnesses available for interviews and provided factual chronologies, timelines, internal summaries, and full forensic images to cooperate with the SEC’s investigation."

PBSJ's deferred prosecution is here (pdf) and the SEC's administrative order against Walid Hatoum is here.

SEC charges PBSJ and former exec for Qatar bribes

Tampa, Florida-based engineering and construction firm PBSJ Corporation agreed Thursday to pay $3.4 million for violating the Foreign Corrupt Practices Act by paying bribes and employing foreign officials to win Qatari government contracts.
PBSJ is now known as Atkins North America Holdings Corporation and no longer offers public stock in the U.S.
UK-based Atkins acquired PBSJ in 2010. The group has 17,000 employees world wide.
The SEC charged Walid Hatoum, a former international marketing director for PBSJ, with violating the FCPA's anti-bribery, internal accounting controls, and books and records provisions, and with false records offenses.
Without admitting or denying the findings, Hatoum agreed to pay a penalty of $50,000.
The SEC didn't go to court. It entered an administrative order against Hatoum. And it used a deferred prosecution agreement to resolve PBSJ's offenses. The DPA has a two-year term.
Kara Brockmeyer, chief of the SEC's FCPA unit, said: “Hatoum offered and authorized nearly $1.4 million in bribes disguised as ‘agency fees’ intended for a foreign official who used an alias to communicate confidential information that assisted PBSJ.”
The foreign official gave Hatoum and PBSJ’s international subsidiary access to "confidential sealed-bid and pricing information," the SEC said. The information helped the PBSJ subsidiary win bids in 2009 for a hotel resort development in Morocco and a light rail transit project in Qatar.
Brockmeyer said PBSJ ignored "multiple red flags that should have enabled other officers and employees to uncover the bribery scheme at an earlier stage."
Once PBSL discovered the offenses, Brokmeyer said, it self-reported them and "cooperated substantially.”

The SEC also alleged that Hatoum offered a job to a second foreign official in return for help after PBSJ lost the Morocco hotel project.

In the deferred prosecution agreement, PBSJ agreed to disgorge $2.8 million with interest of $140,000, and pay a penalty of $375,000.
"Even though the bribes themselves were not consummated before the scheme was uncovered by the company, PBSJ earned approximately $2.9 million in illicit profits because it continued work on the [Qatar] light rail project until a replacement company could be found," the SEC said.
The SEC said: "PBSJ took quick steps to end the misconduct after self-reporting to the SEC, and the company voluntarily made witnesses available for interviews and provided factual chronologies, timelines, internal summaries, and full forensic images to cooperate with the SEC’s investigation."
PBSJ's deferred prosecution is here (pdf) and the SEC's administrative order against Walid Hatoum is here.
- See more at: http://www.fcpablog.com/blog/2015/1/22/sec-charges-pbsj-and-former-exec-for-qatar-bribes.html#sthash.fPNc8k8F.dpuf

SEC charges PBSJ and former exec for Qatar bribes

Tampa, Florida-based engineering and construction firm PBSJ Corporation agreed Thursday to pay $3.4 million for violating the Foreign Corrupt Practices Act by paying bribes and employing foreign officials to win Qatari government contracts.
PBSJ is now known as Atkins North America Holdings Corporation and no longer offers public stock in the U.S.
UK-based Atkins acquired PBSJ in 2010. The group has 17,000 employees world wide.
The SEC charged Walid Hatoum, a former international marketing director for PBSJ, with violating the FCPA's anti-bribery, internal accounting controls, and books and records provisions, and with false records offenses.
Without admitting or denying the findings, Hatoum agreed to pay a penalty of $50,000.
The SEC didn't go to court. It entered an administrative order against Hatoum. And it used a deferred prosecution agreement to resolve PBSJ's offenses. The DPA has a two-year term.
Kara Brockmeyer, chief of the SEC's FCPA unit, said: “Hatoum offered and authorized nearly $1.4 million in bribes disguised as ‘agency fees’ intended for a foreign official who used an alias to communicate confidential information that assisted PBSJ.”
The foreign official gave Hatoum and PBSJ’s international subsidiary access to "confidential sealed-bid and pricing information," the SEC said. The information helped the PBSJ subsidiary win bids in 2009 for a hotel resort development in Morocco and a light rail transit project in Qatar.
Brockmeyer said PBSJ ignored "multiple red flags that should have enabled other officers and employees to uncover the bribery scheme at an earlier stage."
Once PBSL discovered the offenses, Brokmeyer said, it self-reported them and "cooperated substantially.”

The SEC also alleged that Hatoum offered a job to a second foreign official in return for help after PBSJ lost the Morocco hotel project.

In the deferred prosecution agreement, PBSJ agreed to disgorge $2.8 million with interest of $140,000, and pay a penalty of $375,000.
"Even though the bribes themselves were not consummated before the scheme was uncovered by the company, PBSJ earned approximately $2.9 million in illicit profits because it continued work on the [Qatar] light rail project until a replacement company could be found," the SEC said.
The SEC said: "PBSJ took quick steps to end the misconduct after self-reporting to the SEC, and the company voluntarily made witnesses available for interviews and provided factual chronologies, timelines, internal summaries, and full forensic images to cooperate with the SEC’s investigation."
PBSJ's deferred prosecution is here (pdf) and the SEC's administrative order against Walid Hatoum is here.
- See more at: http://www.fcpablog.com/blog/2015/1/22/sec-charges-pbsj-and-former-exec-for-qatar-bribes.html#sthash.fPNc8k8F.dpuf

SEC charges PBSJ and former exec for Qatar bribes

Tampa, Florida-based engineering and construction firm PBSJ Corporation agreed Thursday to pay $3.4 million for violating the Foreign Corrupt Practices Act by paying bribes and employing foreign officials to win Qatari government contracts.
PBSJ is now known as Atkins North America Holdings Corporation and no longer offers public stock in the U.S.
UK-based Atkins acquired PBSJ in 2010. The group has 17,000 employees world wide.
The SEC charged Walid Hatoum, a former international marketing director for PBSJ, with violating the FCPA's anti-bribery, internal accounting controls, and books and records provisions, and with false records offenses.
Without admitting or denying the findings, Hatoum agreed to pay a penalty of $50,000.
The SEC didn't go to court. It entered an administrative order against Hatoum. And it used a deferred prosecution agreement to resolve PBSJ's offenses. The DPA has a two-year term.
Kara Brockmeyer, chief of the SEC's FCPA unit, said: “Hatoum offered and authorized nearly $1.4 million in bribes disguised as ‘agency fees’ intended for a foreign official who used an alias to communicate confidential information that assisted PBSJ.”
The foreign official gave Hatoum and PBSJ’s international subsidiary access to "confidential sealed-bid and pricing information," the SEC said. The information helped the PBSJ subsidiary win bids in 2009 for a hotel resort development in Morocco and a light rail transit project in Qatar.
Brockmeyer said PBSJ ignored "multiple red flags that should have enabled other officers and employees to uncover the bribery scheme at an earlier stage."
Once PBSL discovered the offenses, Brokmeyer said, it self-reported them and "cooperated substantially.”

The SEC also alleged that Hatoum offered a job to a second foreign official in return for help after PBSJ lost the Morocco hotel project.

In the deferred prosecution agreement, PBSJ agreed to disgorge $2.8 million with interest of $140,000, and pay a penalty of $375,000.
"Even though the bribes themselves were not consummated before the scheme was uncovered by the company, PBSJ earned approximately $2.9 million in illicit profits because it continued work on the [Qatar] light rail project until a replacement company could be found," the SEC said.
The SEC said: "PBSJ took quick steps to end the misconduct after self-reporting to the SEC, and the company voluntarily made witnesses available for interviews and provided factual chronologies, timelines, internal summaries, and full forensic images to cooperate with the SEC’s investigation."
PBSJ's deferred prosecution is here (pdf) and the SEC's administrative order against Walid Hatoum is here.
- See more at: http://www.fcpablog.com/blog/2015/1/22/sec-charges-pbsj-and-former-exec-for-qatar-bribes.html#sthash.fPNc8k8F.dpuf

Orange and Rockland Utilities Failed to Notify Insurer of Hazard; New York Appellate Division Rules that Travelers Insurance no longer is required to cover the Utility Company for the Cleanup of Hazardous Waste at Seven MGP Plants

Orange and Rockland Utilities Failed to Notify Insurer of Hazard; New York Appellate Division Rules that Travelers Insurance no longer is required to cover the Utility Company for the Cleanup of Hazardous Waste at Seven MGP Plants




Source: http://www.newyorklawjournal.com, January 21, 2015


An insurance company no longer is required to cover an upstate New York utility company for the cleanup of hazardous waste at seven plants that provided gas lamps during the 1800s and early 1900s, an appellate court has ruled.

The Appellate Division, First Department, found earlier this month that Travelers Indemnity Company does not have to provide coverage to Orange and Rockland Utilities because the insured, as required under its policy, failed to give timely notice of possible pollution at the now-shuttered gas plants.

The panel of Justices John Sweeny Jr. (See Profile), Richard Andrias (See Profile), Rosalyn Richter (See Profile) and Darcel Clark (See Profile) decided Travelers Indemnity Company v. Orange and Rockland Utilities, 60360102. In doing so, it upheld Manhattan Justice Eileen Bransten’s (See Profile) decision to grant summary judgment in favor of Travelers.
“Defendant’s argument that it never had actual notice of any pollution was insufficient,” the panel said in a brief, unanimous opinion. “The record abounds with documents demonstrating that pollution likely existed at each of the sites. … These documents, along with repeated interactions with both state and federal regulators, were sufficient to place defendant on notice.”

The manufactured gas plants were operated from 1852 to 1965 in Middletown, Port Jervis, Suffern, Haverstraw and Nyack.


The dates of the policies under which Orange and Rockland or its predecessors were issued coverage range between 1955 and 1978. Travelers argued that the utility was required to give notice 14 years before it did so in 1995.

According to Bransten’s ruling, there were several instances showing the utility’s knowledge about pollution issues. For example, the utility notified the Environmental Protection Agency in 1981 that there was “possible residual” from manufacturing gas at three plants; the utility investigated coal tar that leaked from a cistern at another site in 1985; and a site inspector retained by the EPA found there was concern that pollution leaching into groundwater would pollute a “glacial … aquifer” near a site in Middletown.

The utility argued that it was not required to provide notice to Travelers until it entered a final consent order with the state Department of Environmental Conservation in 1995 requiring the investigation of pollution at its gas plants and remediation of sites found to be contaminated.

The appellate court also rejected Orange and Rockland’s argument that it was unaware of the pollution because it had an “apparent strategy of waiting to be directed by the appropriate regulatory agencies to investigate the sites and remediate pollution” when there was strong evidence of the contamination problem.

Bransten noted the utility said in a 2008 case that it did not investigate any of the gas plant sites. “Now, ORU makes contradictory representations, stating that it in fact conducted investigations at [manufactured gas plant] sites, and that these investigations were sufficient to cause it to maintain a good faith belief that the policies would be implicated, notwithstanding internal reports and regulatory interactions to the contrary,” Bransten said in a July 2013 opinion.

The utility was aware of a reasonable possibility that its insurance policies would be implicated, which is the standard the First Department set out in its 2010 decision in Travelers Indemnity Company v. Orange & Rockland Utilities, Bransten said.

Families seek damages over ‘dangerous’ asbestos at 3 closed Ocean View, California schools

Families seek damages over ‘dangerous’ asbestos at 3 closed Ocean View, California schools




Damages are being sought by the families of some students who attended three elementary schools in the Ocean View School District that are temporarily shut because of asbestos concerns that arose late last year.

A claim filed with Ocean View on Dec. 19 alleges that the district, its elected leaders, various officials and contractors failed to protect students from “hazardous and unsafe” conditions at Hope View, Lake View and Oak View elementary schools between July and October. A claim is the first step in a process that could lead to a lawsuit.

The three Huntington Beach schools were closed indefinitely in October after asbestos was discovered during a modernization project at 11 campuses that began in July. The resulting asbestos cleanup process displaced more than 1,600 students, who are being bused to eight other campuses in four school districts. It also caused the district to spend unplanned millions for cleanup and related costs.

The claim alleges that students at the three schools inhaled “dangerous quantities of toxic asbestos fibers” due to negligent actions of the district and its contractors. Exposure to asbestos, the claim says, caused emotional distress for students, whose names the school district redacted from the filing. It was unclear how many students the claim represents.
The filing seeks an unspecified amount for past and future medical costs.

Attorneys for the school district and the families could not immediately be reached for comment Wednesday.

Asbestos that hasn’t been disturbed isn’t harmful to people, but it can become a hazard when the dust becomes airborne. Inhaling high levels of asbestos over a long period can cause cancer and other lung disease, experts say.

In October, asbestos was not detected in independent surface tests in classrooms at Lake View Elementary, according to Mohsen Nazemi, deputy executive officer for engineering and compliance for the South Coast Air Quality Management District.

According to district documents, previous test results at Lake View showed airborne asbestos in two classrooms higher than levels set in the federal Asbestos Hazard Emergency Response Act, which regulates how much asbestos can be present in public buildings like schools.

At Hope View, a sample taken in one classroom contained a single asbestos fiber. No air samples taken at Oak View were above the legal threshold, according to district documents.
When the schools were built decades ago, asbestos was used as fireproofing on metal beams above the ceilings. Over time, asbestos dust began to fall from the beams and settle on classroom ceiling tiles, district records show.

Tests at eight other schools showed no significant level of asbestos in the air, the district said.

In August, the AQMD cited a contractor working at Mesa View Middle School in Huntington Beach, saying the contractor removed roofing tiles that contained asbestos without using proper safeguards.

THERE WAS NOT ENOUGH WATER TO FIGHT THE AVALON OF EDGEWATER FIRE. THE INFRASTRUCTURE HAS BEEN UNDERSIZED FOR THE SIZE OF THE DEVELOPMENTS BUILT IN EDGEWATER


THERE WAS NOT ENOUGH WATER TO FIGHT THE AVALON OF EDGEWATER FIRE.  THE INFRASTRUCTURE HAS BEEN UNDERSIZED FOR THE SIZE OF THE DEVELOPMENTS BUILT IN EDGEWATER




Bergen County Prosecutor’s Office arson squad says that they are 100% certain that the fire was accidental.  Perhaps, but there is Gross Negligence involved in the Design, Sprinkler System Design, and Lack of Firefighting Water

Maintenance workers accidentally sparked the blaze that torched an Edgewater apartment complex Wednesday and displaced more than 1,000 people, officials said.

Gov. Chris Christie and local officials on Thursday night confirmed that maintenance workers performing plumbing work with a blowtorch started the fire.

After the fire started in the walls of a first floor apartment, the workers called a supervisor before calling 911, Police Chief William Skidmore said. It took 15 minutes before the call was made, a long time in a fire, he said.

But the delay wasn't criminal, Skidmore said.  However, the owners are responsible for hiring individuals who do not know what they doing.  It blows our mind that a blowtorch fire can destroy a 240-unit luxury building that has a sprinkler system; unless of course the sprikler system was inadequate, undersized, lack of firefighting water, and so on.

"It was an accident," he said. "It was a tragic accident, but that's what it was. It was not a criminal act."




The cause of the fire was determined by an investigation by the Bergen County Prosecutor’s Office arson squad.

Chistie, along with county and local officials, revealed these details in a press conference outside the Edgewater Community Center, where the town is providing aid to displaced residents. The governor and his cabinet huddled with Bergen County Executive James Tedesco, Mayor Michael McPartland and local emergency responders before greeting relief workers and victims of the fire.

Gov. Christie and police chief say Edgewater fire accidental In a press conference at the Edgewater Community Center, Gov. Chris Christie and William Skidmore, the Edgewater Police Chief, said that the massive fire was accidental but that an investigation into the building codes would be conducted. 
 
He said he wanted to assure victims that the state was working to ensure the "transition" after the fire was as smooth as possible.

"At times like this most people are concerned they'll be forgotten," Christie said. "That's why I'm here, to make sure people know that we won't forget."

Christie said the state would conduct a separate investigation to ensure the building met current fire codes. He also said the state may review current fire codes in the wake of the fire.

Edgewater Fire Chief Tom Jacobson said earlier the lightweight, wooden construction of the Avalon Bay complex allowed the flames to spread so rapidly. In a statement released Thursday afternoon, AvalonBay Communities, owners of the complex, said the building met fire and safety codes.

"The purpose of those codes is not to prevent the building from burning down, but rather to ensure that there is sufficient time and opportunity for all occupants to exit safely in the event of a fire," the company wrote. "We are grateful that everyone at Avalon at Edgewater was able to leave the building and get to safety without serious injury."

A spokesman declined to immediately comment on the results of the arson squad investigation.





Undersized Sprinkler System and Lack of Water Volume and Pressure
 


For all of us who live in Edgewater the water pressure has been a big issue for many years, especially in the new part of Edgewater where the new developments took place in the 1990s and onward.  We have been warning people about the shoddy construction implemented by well-connected firms.  

These firms installed undersized water piping that can only carry a certain amount of water and under a certain pressure.  There was simply not enough water to fight the fire at Avalon and the firefighters lost some very valuable time in trying to put the fire under control.  They made statements to that effect and they had to bring in fireboats to fight the fire, but it was too late.  In fact, the videos that the news networks' helicopters took are very revealing:  they show the very weak water stream that was being used to put out the fire;  there was simply inadequate water and the water was barely reaching the middle of the fire.




The above opinion is supported by the statements of Bogota Fire Battalion Chief Joe DiMauro who explained to WCBS 2, "If you hit the hydrant in so many locations, it lowers the pressure." The FDNY Tweeted, "FDNY Marine 1's fireboat 343 is heading to Edgewater, NJ, to assist with 5-alarm fire." 

In other developments in Edgewater, people have been complaining about the low water pressure that their homes have.  Upon further inquiries at the time, we discovered that there is simply not enough pipe diameter to carry both the fire suppression water and the domestic use water.  Shoddy and cost-cutting developer's work, who were well-connected in Edgewater and got all that substandard work approved by the Borough.
 
This is a tragedy that should have never happened.   The Borough officials have let the people down by approving shoddy construction and undersized fire suppression and fire fighting systems.