paDEP Fines
Vantage Energy Nearly $1 Million for Landslide and ILLEGAL WASTE DISPOSAL at
Greene County Well Pad.
COMMONWEALTH OF PENNSYLVANIA
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
FOR IMMEDIATE RELEASE
12/22/2014
CONTACT:
John Poister, DEP Southwest Regional
Office
412-442-4203
DEP Fines Vantage Energy Nearly $1
Million for Landslide and Other Problems at Greene County Well Pad.
PITTSBURGH -- The Department of
Environmental Protection (DEP) has signed a Consent Order and Agreement with
Vantage Energy Appalachia, LLC, fining the company $999,900 for more than a
dozen violations of environmental regulations stemming from a landslide and
illegal waste disposal at their Porter Street well pad in Franklin Township,
Greene County, earlier this year.
On January, 16, 2014, DEP learned that
landslide occurred at the well pad the previous day. DEP inspectors immediately
responded and noted that the slide impacted the side of the well pad and had
dropped about 40 feet downslope to where it encroached upon two streams.
The slide continued to grow
substantially and eventually covered the two streams. DEP threatened to order a
shutdown of all activity on the well pad. In response, the company, on March
28, agreed to voluntarily stop drilling operations and to make interim action
to prevent further movement of the slide. DEP cited the company for numerous
violations of the state’s Oil and Gas Act and Clean Streams Law.
On July 14, Elite Well Services, a
Vantage contractor, dumped two truckloads (about 200 barrels) of drilling
wastewater down the side of the well pad where the interim stabilization
activities were occurring. The wastewater impacted the landslide area being
restored and ended up in the streams originally impacted by the slide.
DEP again cited the company for further violations of various environmental
statutes including the Oil and Gas Act.
On July 21, the company submitted a
notice of its intent to remediate the soils, surface water and groundwater
impacted by release of the wastewater. But, even as they began those efforts,
DEP learned that Vantage had constructed a new access road along the streams
impacted by the slide and the waste discharge. The construction was not
authorized under the company’s erosion and sediment permit. The company
was cited again.
On December 16, Vantage and DEP signed
the Consent Order and Agreement (COA) that establishes enforceable milestones
for Vantage to correct the violations at the well site and requires the full
restoration of impacted streams and wetlands, permanent stabilization of the well
pad, and remediation of the soils, surface water and groundwater impacted by
the illegal disposal of the wastewater.
“These violations resulted in significant damage to our natural resources and this action is in direct response to the seriousness of the violations,” John Ryder, Director of District Oil and Gas Operations for DEP said. “To its credit, Vantage has begun to make a genuine effort to better manage and operate their well sites. The company has hired an independent consultant to conduct an environmental audit of all of their well sites in Pennsylvania and the company is now fully cooperating with DEP.”
“These violations resulted in significant damage to our natural resources and this action is in direct response to the seriousness of the violations,” John Ryder, Director of District Oil and Gas Operations for DEP said. “To its credit, Vantage has begun to make a genuine effort to better manage and operate their well sites. The company has hired an independent consultant to conduct an environmental audit of all of their well sites in Pennsylvania and the company is now fully cooperating with DEP.”
By signing the COA, the company also
agreed to the $999,900 fine, one of the largest imposed on a driller by DEP
this year. The COA also stipulates further penalties if project deadlines are
not met. As part of the agreement, the company will also provide written
“progress reports” detailing the actions taken during each period to comply
with the requirements of the COA. The company must complete all the work on the
site, meeting all DEP regulations, by December, 31, 2015.