| 
An
  OSHA investigation of the incident resulted in allegations that the
  employer’s process safety management (PSM) program was woefully incomplete.
  Arboris had completed some aspects of PSM required by OSHA, but its program
  had significant gaps—and in those gaps were the makings of disaster. Take a
  close look at your own PSM program, and make sure you haven’t missed any of
  these preventive measures. 
Complete Your Process
  Safety Information
Arboris
  was cited for multiple violations of 29 CFR 1910.119(d), which requires
  employers to develop complete process safety information for use in the
  development of safety practices and procedures. Arboris allegedly did not
  have complete information for its process with respect to:  
The
       maximum intended inventory. There was no record of how much inventory
       the system could handle.Safe
       upper and lower limits for temperature, pressures, flows and
       compositions. Without a maximum intended inventory, there was no way to
       adequately determine this information.An
       evaluation of the consequences of deviations from safe limits in the
       process. If you haven’t determined what the limits are, it’s impossible
       to determine what deviations might do. Accurate
       piping and instrumentation diagrams (P&ID). According to the
       existing P&ID, the relief piping on the tank that exploded vented to
       the ground, when, in fact, it did not. 
Its
       relief system design and design basis. There should be some evaluation
       of how the relief system is supposed to work. Design
       codes and standards employed. What information was used in developing
       the system design? The information the employer had in this case did not
       match the system as designed.Safety
       systems. There was no information in the employer’s process safety
       documentation about foam suppression systems, flame arrestors,
       interlocks, level indicators, or lower explosive limit (LEL) meters. Recognized
       and generally accepted good engineering practices (RAGAGEP). OSHA
       alleges that Arboris failed to document that nine different components
       of the process were installed in accordance with good engineering
       practices. 
Without
  complete process information, Arboris lacked what it needed to ensure that
  the process was properly designed and operating within safe limits.  
Action item: Is your
  process safety information complete and current? 
Complete Your Process
  Hazard Analysis
Arboris
  was also cited for multiple violations of 29 CFR 1910.119(e) requiring
  employers to perform a process hazard analysis (PHA), which must be
  periodically updated. Arboris had performed a PHA, but it was incomplete. The
  PHA allegedly failed to: 
Identify
       all potential worst-case scenarios that could lead to an
       overpressurization of its process.Identify
       the potential for the hexane solvent wash to rapidly boil under upset
       conditions.Identify
       the potential hazards of material build-up in the relief pipe.  
Arboris
  also allegedly failed to analyze and characterize the hazards created by
  facility siting in both its initial PHA and follow-up PHAs. Neither PHA
  addressed facility siting at all. A complete PHA of facility siting should
  examine the hazards of location, unit layout, storage/warehouses, spacing
  between process components, control rooms, occupied buildings, unit location
  relative to surroundings, emergency stations, contingency planning,
  electrical classification, ventilation, location of emergency relief venting,
  and evacuation routes through perimeter fencing surrounding the covered
  process. 
 
Of course,
  when your PHA is finished, you must arrange to address any items of concern
  that have been identified. Arboris allegedly also failed to do this; it had
  no system to promptly address its PHA findings and recommendations, assure
  that they would be addressed in a timely manner, and document those actions.  
Action items: Does your
  PHA cover all possible worst-case scenarios and dangerous chemical reactions,
  as well as the hazards inherent in your location and layout? Have you
  addressed your findings? Have you communicated the findings and your
  corrective measures to process operators?  
Develop Safe Operating
  Procedures
This is
  the point where the rubber met the road at the Arboris plant. There does seem
  to have been a written set of operating procedures in place, but workers were
  not following it when they added hexane wash to the melt tank—the event that
  led directly to the explosion. 
 
The
  workers may not have been following the procedures because the procedures
  themselves were incomplete, failing to cover all possible situations in
  violation of 29 CFR 1910.119(f). Specifically, the written procedures did not
  cover: 
Temporary
       operations.Startup
       following a turnaround or emergency shutdown.Consequences
       of deviation. In this case, OSHA noted that the procedures did not cover
       the consequences of adding hexane to the process before it reached the
       optimal temperature.Steps
       required to correct or avoid deviation.Safety
       systems and their function.Special
       situations, such as lockout/tagout, confined space entry, pipe
       breaking/line breaking operations, and the presence of workers not
       directly involved in the operation in the work area.Annual
       review of the operating procedures. 
Action items: Do your
  operating procedures cover all
  operating conditions, not just “normal production”? Do they give operators
  the information they will need to correct problems that might arise before
  they lead to disaster?  
Manage Any Changes
Any time
  you make changes to a covered process other than to replace existing parts or
  ingredients with essentially similar ones, you must examine the changes from
  all angles in order to make sure that the process will remain safe. On the
  day of the fire, Arboris workers used a different chemical in their
  process—isohexane, rather than the designed n-hexane—but it appears that no
  one stopped to ask whether the change was safe.  
 
Action item: Ensure that
  you have written management-of-change procedures, and that operators
  understand that any changes to the process must be managed using those
  procedures.  
 
Tomorrow,
  we’ll look at six more gaps that OSHA identified in Arboris’ PSM program that
  could have helped to prevent the fire.  
 |