An Analysis of International Transformer Failures, Part 1
Introduction
Major
losses involving large oil-cooled transformers continue to occur on a
frequent basis. A working group of the International Association of
Engineering Insurers (IMIA) (www.imia.com)
was established in 1995 to examine this topic and presented a report at
the 1996 Conference. The magnitude of the losses has increased
significantly since the last study. Increased equipment utilization,
deferred capital expenditures and reduced maintenance expenses are all
part of today's strategies for transformer owners. To make matters
worse, world power consumption is increasing, and the load on each aging
transformer continues to grow.
Scope of the Study
A
request was sent to all IMIA national delegations seeking information
on losses of transformers rated at 25 MegaVoltAmperes (MVA) and above
for the period 1997 through 2001. Information was requested concerning
year of loss, size in MVA, age at failure, application (such as
utilities, industrials), cause of failure, property damage portion, and
business interruption portion. Data was obtained on 94 cases. An
estimate of the total population of power transformers would have been
useful, but it is impractical to obtain this information. Some of the
contributors were not able to identify the age of the transformers, and
in some cases, the size of the transformer. The analysis is annotated
wherever data is missing. All amounts of losses were converted to U.S.
dollars, using the following exchange rates: 0.9278 euros; 8.542 Swedish
kronas; and 6.0858 French francs.
Five-Year Trend
During
this period, the number of transformer claims reached a peak (25) in
1998. But, the dollars paid out, reached a maximum in 2000 due to
several claims in the multi-million dollar range, plus one large
business interruption loss. The largest transformer loss also occurred
in 2000, at a power plant, with a business interruption portion the
equivalent of more than U.S. $86 million. Three of the top four property
damage claims were in industrial plants.
Table 1 displays the
annual transformer claims. Not all of the data contributed had size
information. Therefore, we could only analyze 78 claims for cost per
size. The average cost (for property damage only) was approximately
$9,000 per MVA (or $9 per kVA). Table 1A displays the annual transformer
claims and cost per MVA.
Type of Application
During
this period, the largest number of transformer claims (38) occurred in
the Utility Substation sector, but the highest paid category was
Generator Step Up transformers, with a total of more than $200millon. If
the extraordinary business interruption loss is ignored, the Generator
Step Up transformer category is still significantly higher than any
other category. This is to be expected due to the very large size of
these transformers. Table 2 displays the annual claims by application.
Cause of Failure
For
the transformer failures reported, the leading cause was "insulation
failure." This category includes inadequate or defective installation,
insulation deterioration, and short circuits, but not exterior surges
such as lightning and line faults. Table 3 lists the number of failures
and percentage of total costs paid for each cause of failure. A
description of each cause category is found below.
The risk of a transformer failure is actually two-dimensional: the frequency of failure and the severity of failure (see "Transformer Asset Management,” The Locomotive, Spring 2003, Vol. 77, No. 2).
Cause of Transformer Failure
Insulation Failures
– Insulation failures were the leading cause of failure in this study.
This category excludes those failures where there was evidence of a
lightning or a line surge. There are actually four factors that are
responsible for insulation deterioration: pyrolosis (heat), oxidation,
acidity and moisture. But moisture is reported separately. The average
age of the transformers that failed due to insulation was 18 years.
Design /Manufacturing Errors
– This category includes conditions such as: loose or unsupported
leads; loose blocking; poor brazing; inadequate core insulation;
inferior short circuit strength; and foreign objects left in the tank.
In this study, this is the second leading cause of transformer failures.
Oil Contamination – This category pertains to those
cases where oil contamination can be established as the cause of the
failure. This includes sludging and carbon tracking.
Overloading
– This category pertains to those cases where actual overloading could
be established as the cause of the failure. It includes only those
transformers that experienced a sustained load that exceeded the
nameplate capacity.
Fire /Explosion – This category
pertains to those cases where a fire or explosion outside the
transformer can be established as the cause of the failure. This does
not include internal failures that resulted in a fire or explosion.
Line Surge
– This category includes switching surges, voltage spikes, line
faults/flashovers, and other T&D abnormalities. This significant
portion of transformer failures suggests that more attention should be
given to surge protection, or the adequacy of coil clamping and short
circuit strength.
Maintenance /Operation – Inadequate or
improper maintenance and operation was a major cause of transformer
failures, when you include overloading, loose connections and moisture.
This category includes disconnected or improperly set controls, loss of
coolant, accumulation of dirt and oil, and corrosion. Inadequate
maintenance is to blame for transformer owners not discovering incipient
troubles when there was ample time to correct them.
Flood
– The flood category includes failures caused by inundation of the
transformer due to man-made or naturally caused floods. It also includes
mudslides.
Loose Connections – This category includes
workmanship and maintenance in making electrical connections. One
problem is the improper mating of dissimilar metals, although this has
decreased somewhat in recent years. Another problem is improper torquing
of bolted connections. Loose connections could be included in the
maintenance category, but we customarily report it separately.
Lightning
– Lightning surges are considerably fewer than in previous studies we
have conducted. Unless there is confirmation of a lightning strike, a
surge type failure is categorized as a Line Surge.
Moisture
– The moisture category includes failures caused by leaky pipes,
leaking roofs, water entering the tanks through leaking bushings or
fittings, and confirmed presence of moisture in the insulating oil.
Moisture could be included in the inadequate maintenance or the
insulation failure category above, but we customarily report it
separately.
An Analysis of International Transformer Failures, Part 2
Introduction
In
our previous discussion of a five-year international study of loss
trends for transformer failures, we concluded that Insulation Failure
was the leading cause. Combined with Design/Material/Workmanship and
Unknown causes, these three categories accounted for 65 percent of the
total number of transformer breakdowns in our study of losses as
reported by members of the International Association of Engineering
Insurers (IMIA) (imia.com) and 85 percent of the total amount paid out
for these claims.
Other causes of loss were spread among: Oil
Contamination; Overloading; Fire/Explosion; Line/Surge; Improper
Maintenance/Operation; Flood; Loose Connection; Lightning and Moisture
(see An Analysis of International Transformer Failures, Part 1, The Locomotive, Winter 2004, Vol. 78, No. 1).
Transformer Aging
We
did not categorize "age" as a cause of failure. Aging of the insulation
system reduces both the mechanical and dielectric-withstand strength of
the transformer. As the transformer ages, it is subjected to faults
that result in high radial and compressive forces. As the load
increases, with system growth, the operating stresses increase. In an
aging transformer failure, typically the conductor insulation is
weakened to the point where it can no longer sustain mechanical stresses
of a fault. Turn-to-turn insulation then suffers a dielectric failure,
or a fault causes a loosening of winding clamping pressure, which
reduces the transformer's ability to withstand future short circuit
forces.
Table 1 displays the distribution of transformer failures
by age. The average age at failure among those transformers in our
study was 18 years.
Table 1 – Distribution of Losses by Age of Transformer
Age at Failure
|
Number of Failures
|
Cost of Failure
|
0 to 5 years |
9
| $11,246,360 |
6 to 10…
|
6
|
$22,465,881
|
11 to 15…
|
9
| $3,179,291
|
16 to 20…
|
9
|
$10,518,283
|
21 to 25…
|
10
| $16,441,930
|
Over 25 Years
|
16
| $15,042,761
|
Age Unknown * |
35
| $ 207,734,306 |
According
to U.S. Commerce Department data, the electric utility industry reached
a peak in new installations in the United States around 1973-74. In
those two years, the country added about 185 GVA of power transformers.
Figure 1 depicts the total transformer additions in the U.S. each year.
Today, these transformers are about 30 years old. With today’s capital
spending on new or replacement transformers at its lowest level in
decades (less than 50GVA /yr), the average age of the entire world
transformer fleet continues to rise.
Figure 1
A risk model of future transformer failures, based on aging, was developed by Hartford Steam Boiler and first published in 2000[1] (The formula appears in “An Analysis of Transformer Failures, Part 1, The Locomotive, Vol. 73, No. 2). The model is based on mortality models that were first proposed in the 19th century.
The
most influential parametric mortality model in published actuarial
literature is that proposed in 1825 by Benjamin Gompertz, who recognized
that an exponential pattern in age captured the behavior of human
mortality. He proposed the failure function:
where f(t) is the instantaneous failure rate, a is a constant; ß is a time constant; and t = time (in years).
In
this article, the author will discuss an updated model for transformer
failure predictions in the coming decade and shares the observations of
industry executives about the condition of the transformer marketplace.
A New Failure Model
HSB’s
first publication on transformer failure predictions used the Gompertz
model. In 1860, W.M. Makeham modified the Gompertz equation because it
failed to capture the behavior of mortality due to accidental death, by
adding a constant term in order to correct for this deficiency. The
constant can be thought of as representing the risk of failure by causes
that are independent of age (or random events such as lightning, or
vandalism).
Subsequent studies by HSB[2, 3]
have adopted the Makeham formula. The Gompertz curve was further
modified by W. Perks, R.E. Beard and others. In 1932, Perks proposed
modifications to the Gompertz formula to allow the curve to more closely
approximate the slower rate of increase in mortality at older ages.
A
more accurate model for transformer failures can be represented by the
Perks formula and was included — for the first time — in connection with
this study based on the IMIA survey of international transformer
failures.
The instantaneous failure rate for transformers in a
given year is the probability of failure per unit time for the
population of transformers that has survived up until time “t.” To
include the frequency of random events (lightning, collisions,
vandalism) separate from the aging component, the constant
“A” is set at 0.005 (which represents one-half percent of 1 percent).
Figure 2 is the corresponding exponential curve for a 50 percent failure
rate at the age of 50.
Figure 2
The
correlation between calendar age and insulation deterioration is
subject to some uncertainty — not all transformers were created equal.
This prediction is a simple statistical model and does not take into
consideration manufacturing differences or loading history. This failure
rate model is based on the calendar age of the transformer, and does
not address material and design defects such as “infant mortality.”
With
a failure rate model and population estimate for each vintage, future
failures can be predicted for the entire fleet of transformers, by
multiplying the failure rate times the population of the vintage:
Number of failures (in GVA) at year "t," = [Failure rate] x [population that is still surviving]
Future Transformer Failures
Using
the population profile from Figure 1, the predicted failures can be
plotted for all U.S. utility transformers built between 1964 and 1992.
The prediction is simply intended to illustrate the magnitude of the
problem facing the utility industry and the insurance industry. Figure 3
is the failure distribution. The X-axis is the year of predicted
failures. The Y-axis is the population of the failures (expressed in
GVA). It should be noted that the graph is a failure rate of those that
survived, until time ("t"). In this graph, a vertical line depicts each
vintage. By 1975, each year has a cluster of six different vintages
(1964, ‘66, ‘68, ’70, ’72 and ’74); and after 1992, each cluster is 15
vintages.
Figure 3
In
our next chart (Figure 4), we take a closer look at predicted failures
over six years (2003-2008). Due to the increased installations, the
failures of 1972 vintage transformers will overtake the failures of the
1964 vintage in the year 2006. By 2008, the number of 1974 vintage
transformers will easily exceed the failures of the 1964-vintage
transformers. This prediction ignores rebuilds and rewinds of previous
failures.
Figure 4
In
order to examine the total predicted transformer failures in any given
year, we can take the sum of the individual vintages, for each year.
Figure 5 illustrates such a prediction.
Although we have not yet
seen an alarming increase in end of life failures, such a rise must be
expected eventually. The most difficult task for the utility engineer is
to predict the future reliability of the transformer fleet, and to
replace each one the day before it fails. Meeting the growing demand of
the grid and at the same time maintaining system reliability with this
aging fleet will require significant changes in the way the utility
operates and cares for its transformers.
Figure 5
Action Plan
One
conservative strategy suggests that the industry start a massive
capital replacement program that duplicates the construction profile of
the 1960s and 1970s. But this would needlessly replace many transformers
and cost the utility industry billions of U.S. dollars.
The
ideal strategy is a life assessment, or life cycle management program,
that sets loading priorities and provides direction to identify: a.)
transformer defects that can be corrected; b.) transformers that can be
modified or refurbished; c.) transformers that should be relocated; d.)
transformers that should be retired. The insurance industry should be
aware that both the Institute of Electrical and Electronics Engineers,
Inc. (IEEE), and the International Council on Large Electrical Systems
(CIGRE) are developing guidelines for aging transformers. [5, 6]
Electric Utilities and the Transformer Industry
The
deregulation of wholesale electricity supply around the world has led
to a number of changes and new challenges for the electric utility
industry and its suppliers. In the last few years, many electric
utilities have merged to form larger international utilities, and others
have sold off their generating assets. All of this is being done in an
attempt to enhance revenue streams, reduce the incremental cost per MW
or react to spot market opportunities.
Years ago, utilities knew
the needs of their native markets and built an infrastructure to keep
pace with those needs, with associated construction costs being passed
back to the ratepayers. Starting in the 1980s, utilities in the United
States had to contend with regulatory mandates to utilize independent
power producers to satisfy supply and meet demand. They were not able to
plan projects for their native load projections. In this environment,
it was possible that the utility's capital projects may not be afforded a
favorable rate structure from the local utility commission in an openly
competitive market. Therefore, many utilities understandably halted
most of their capital spending, due to this regulatory uncertainty.
This
significantly limited the activity taking place in terms of expanding
the industry's infrastructure, including their transmission and
distribution assets. In the 1990s, capital spending on new and
replacement transformers was at its lowest level in decades. Many of the
major manufacturers exited the power transformer business. Many of the
remaining manufacturers have undertaken cost-cutting measures to
survive.
"The Boom is Over..."
Then
in 1999-2000, the transformer market experienced a brief upswing in
activity primarily due to a rush to build gas-turbine generating plants.
The demand for generator step-up transformers in the United States
almost doubled during these peak months. At that time, there were
predictions that 750 Gigawatts of new generating capacity would be
installed worldwide between 2000 and 2010.
But, the rush to build
power plants in the United States has subsided; many of the energy
companies are now drowning in debt. Many developers and investors had to
sell their interests in existing plants in order to finance the
completion of new plants. In 2001, projects worth 91 GW of generating
capacity in the United States were cancelled (out of 500 GW). And in the
first quarter of 2002, orders for 57 GW of capacity were cancelled.
Again,
capital spending in the utility industry sharply declined. According to
Dennis Boman, director of marketing, ABB Inc. Power Transformers, "the
decline has far exceeded anyone's prediction to levels that post-dated
the increase. Within a short six-month period, the power transformer
market dropped by over 50 percent,” he said. Added Joe Durante, vice
president, VA Tech Elin Transformers, "...the boom of the late 1990s and
early 2000 is over, and most likely won't be seen for another 30 years.
Replacement opportunities will continue to remain flat and customer
spending will continue only when necessary."
Based on Hartford
Steam Boiler claim experience, new transformer prices are significantly
lower than they were a few years ago. It is truly a buyer's market. New
power transformers are being sold at a price less than the cost of a
rewind, and the manufacturers are now providing three-year and five-year
warranties.
Peter Fuchs, vice president sales and marketing,
Geschaftsgebiet Transformers (Siemens), predicts “a stagnant market, on
average, for the United States , Europe and the Far East .” However, “in
other parts of the world, economic growth and business development are
proceeding at high levels, including a resurgence in Asia ,” he
continued. “The need for power in this area already exists, and as
international funding becomes available, we expect to see increased
activity in this region.”
Transmission Growth Opportunities?
Today,
many of the transformer manufacturing plants and repair facilities have
very little activity. Is this "slump" in the market due solely to
government regulation —or deregulation? The three major manufacturers
point to a number of different problems. According to Bowman of ABB, “We
have seen a shift in focus to ‘first cost’ buying with little regard
for any long term impact on buy decisions." Many buyers are choosing the
lowest bidder, with little regard to quality, reliability or factory
service. Fuchs of Siemens observes that “in addition to the price-driven
decision, there is very little technical evaluation, and
‘price-dumping’ continues to go unpunished." Durante of VA Tech Elin
confirms that the major obstacle is "ongoing deregulation uncertainty
which is hindering capital investment.”
Durante believes that the
next growth opportunity in the North American utility market is the
transmission segment. This includes inter-tie transformers,
phase-shifter transformers and autotransformers. "However, this market
is heavily influenced by government regulations and decisions,” he
added.
The U.S. Federal Energy Regulatory Commission (FERC) has
mandated that all generators have equal access to transmission systems
and required integrated utilities to turn over their transmission
systems to independent entities. Some utilities have decided to sell
their transmission assets and purchase transmission service. Other
utilities are joining together and rolling their transmission assets
into limited liability companies. But many utilities first want to
understand exactly how transmission will be regulated. In other words,
utility investors want to know whether the U.S. federal government or
state governments will regulate the transmission assets. Until this is
clear, overall capital spending will be deferred.
Summary
Electricity
is much more than just another commodity. It is the life-blood of the
economy and our quality of life. Failure to meet the expectations of
society for universally available low-cost power is simply not an
option. As the world moves into the digital age, our dependency on power
quality will grow accordingly. The infrastructure of our power delivery
system and the strategies and policies of our insureds must keep pace
with escalating demand. Unfortunately, with regulators driving toward
retail competition, the utility business priority is competitiveness and
related cost-cutting — and not reliability.
References
- William
H. Bartley, HSB, Analysis of Transformer Failures, Proceedings of the
Sixty-Seventh Annual International Doble Client Conference, Boston MA ,
2000.
- William H. Bartley, HSB, Failure History of
Transformers-Theoretical Projections for Random Failures, Proceedings of
the TJH2B TechCon, Mesa AZ , 2001.
- William H. Bartley, HSB,
Transformers Failures, presented as Keynote Address at the annual ABB
Technical Conference, Alamo , TN , 2003.
- Tim Higgins,
Mathematical Models Of Mortality, presented at the Workshop on Mortality
Modeling and Forecasting, Australian National University , February
2003.
- IEEE C57.140, Draft 9 March, 2003 , IEEE Guide for the
Evaluation and Reconditioning of Liquid Immersed Power Transformers,
Rowland James & William Bartley Co- Chair.
- CIGRE 12-20 Guide on Economics of Transformer Management (draft 23.7.02).
========================
An Analysis of Transformer Failures, Part 1 – 1988 through 1997
Transformers Losses Are Significant
As
an object class, transformers have consistently been ranked in the top
five objects for claims paid by Hartford Steam Boiler during the past
several decades. Over the years, HSB has investigated thousands of
transformer losses. Some were covered claims and some were not. Using
the data collected, HSB has conducted a number of studies on transformer
losses and published them in The Locomotive.
In
previous analyses, we examined Initial Parts to Fail, Age at Failure,
and Cause of Failure. To improve our loss experience for transformers,
the most recent study was conducted last year, and covers a 10-year
period from 1988 through 1997. In 1999, we deleted the Initial Parts
category and added two new categories: the Size and Frequency of
Failures, and Where the Failures Were Occurring (by industry or
occupancy).
10-Year Trend - Losses by Transformer Type
Over
the past 10 years, HSB has paid hundreds of transformer claims that
represent many millions of dollars. Chart No. 1, below, shows a
breakdown of claims, according to the transformer type. The chart shows
power transformers, askarel-filled (PCB), dry type, arc furnace,
induction furnace, and rectifier transformers. Except for 1988, the
power transformer dominates our loss history.
Chart No. 1
Occupancies Where Failures Occurred
HSB
insures literally hundreds of different types of occupancies: shopping
malls, bakeries, apparel manufacturers, electric utilities and steel
mills. In order to analyze the transformer risk, we divided this long
list of occupancies into 10 categories we call exposure groups. An
exposure group is a set of occupancies with similar equipment,
operations and loss profiles. Table 1, below, lists the 10 exposure
groups, and identifies some specific examples within those groups.
Table No. 1
Frequency and Severity
In his book, Risk-Based Management: A Reliability-Centered Approach1,
HSB’s Dr. Rick Jones defines "risk" as the product of probability and
consequence, or in insurance engineering terms, the frequency and
severity of the losses. The severity can be defined as the average
annual gross loss, and the frequency (or probability) can be defined as
the average number of losses, divided by the population. Since we don’t
have a true transformer population, we needed to make a substitute.
Because we are ranking the relative risk of exposure groups, we used the
number of locations insured in each group for our "population." Thus,
for any given exposure group:
Frequency equals the Number of Losses divided by the Number of Locations.
(For
example, if we have had an average of 10 losses per year, in a given
exposure group and we insure 1,000 locations in that group, the
probability of a failure is .01 each year, at any location in that
group.) Therefore, we can rank our transformer risk by occupancy, using
the product of frequency and severity. (Risk = Frequency x Severity).
The
graph below, Chart No. 2, is a Frequency-Severity "scatter plot" for
transformer risks in our 10 exposure groups, based on the last 10-year
period. With each group plotted, frequency on the X axis and severity
(or average gross loss) on the Y axis, the X-Y plot becomes a risk
coordinate system. The diagonal lines are called equivalent lines of
risk (for example, a probability of 0.1 for $1,000 and a probability of
0.01 for $10,000 can be considered an equal risk.) Coordinates in the
upper right quadrant are the highest risk.
Chart No. 2
When
frequency and severity of loss are taken into consideration, (as shown
in Chart No. 2), the highest risk is electric utilities. Primary metals
and manufacturing are second and third.
Transformer Age
Transformer
design engineers tell us that a transformer can be expected to last 30
to 40 years under "ideal conditions." But, that is clearly not the case.
In the 1975 study, it was found that the average age at the time of
failure was 9.4 years. In our 1985 study, the average age was 11.4
years. In this study, the average age at failure was 14.9 years. One
would expect to see a "bathtub curve" with infant mortality in the early
years, and aging equipment at the far right. Instead, our claim
statistics show that transformers do not have an indeterminate life.
Chart No. 3, below, shows the age statistics for this study. These
statistics should justify the time and expense to periodically check the
condition of the transformer.
Chart No. 3
The
age of transformers in the electric utility industry deserves special
attention. The United States went through massive industrial growth in
the post World War II era, causing a large growth in base infrastructure
industries, especially the electric utilities. This equipment was
installed from the 1950s through the early 1980s. The way it was
designed and operated, most of this equipment is now in the aging part
of its life cycle. According to U.S. Commerce Department data, the
electric utility industry reached a peak in new installations in the
United States around 1973-74. Today, that equipment is 25 years old.
With today’s capital spending on new and replacement transformers at its
lowest level in decades, the average age of the installed U.S.
transformer fleet continues to rise.
There are actually two
problems here: our nation’s transformer fleet is aging, and to compound
this, the load on each transformer, (or its utilization), continues to
grow. While installation of new transformers is declining, power
consumption continues to grow at a rate of about 2 percent per year.
Capital deferment has led to the increased overall utilization of
transformers in the United States. Due to the steady growth in power
consumption over the last 20 years, it is obvious that the utilization
factor for transformers has increased significantly.
Summary
[In Part 2
of this article: The author discusses the causes of transformer
failure, including lightning surges, line surges, poor workmanship,
deterioration of insulation, overloading and other factors. He
recommends a good maintenance program and concludes with several
recommendations to help achieve maximum service life.]
[Footnotes: 1 R.B. Jones, Risk-Based Management: A Reliability-Centered Approach, Gulf Publishing Co., Houston, TX, 1995]
An Analysis of Transformer Failures, Part 2: Causes, Prevention, and Maximum Service Life
Introduction
Over
the years, Hartford Steam Boiler has investigated thousands of
transformer failures, compiling an extensive database of loss
information. In part one of this article, the author used data from
HSB’s latest 10-year study of transformer claims to examine the types of
breakdowns, frequency, severity, and the issue of transformer age. In
part two, he discusses the causes of transformer failures, recommends a
maintenance program and concludes with ways to help achieve maximum service life.
Cause of Failure
Hartford
Steam Boiler has collected information about transformer failures for
decades. Analysis has shown that while aging trends and utilization may
change (see part 1), the basic causal factors of these failures remain
the same. In the article "Factors Affecting the Life of Insulation of
Electrical Apparatus," published in the July 1949 issue of The
Locomotive, HSB’s J.B. Swering, chief engineer of the Electrical
Division, wrote:
"There are a number
of factors which affect the life expectancy of insulation and these
should receive the careful consideration of persons responsible for the
operation of electrical equipment. These factors include:
- Misapplication
- Vibration
- High Operating Temperature
- Lightning or Line Surges
- Overloading
- Care of Control Equipment
- Lack of Cleanliness
- Care of Idle or Spare Equipment
- Improper Lubrication
- Careless or Negligent Operation
It’s
still good advice, a half-century later. Table 3 shows the primary
cause of transformer failures reported to HSB over the last several
decades, and identifies those areas where failure-reducing efforts can
best be directed. The table lists the most common causes of failures and
the percentage of all the failures they represent for the studies
conducted in 1975, 1983 and 1998. However, the 1998 study did not use
the same methodology for categorizing the causes. The information is
presented here for comparison purposes, but no conclusions on trends
should be made.
Table 3: Primary Cause of Transformer Failures
Lightning
Lightning
surges are considerably less than previous studies, because of our
changes in categorizing the cause. Today, unless we have confirmation of
a lightning strike, a surge type failure is categorized as "Line
Surge." This is one of the departures from the previous studies.
Line Surges
According
to our database, the Line Surge (or Line Disturbance) is the number one
cause for all types of transformers failures. This category includes
switching surges, voltage spikes, line faults/flashovers, and other
transmission and distribution (T&D) abnormalities. This significant
portion of transformer losses indicates that more attention should be
given to providing surge protection, or testing the adequacy of existing
surge protection.
Poor Workmanship/Manufacturer
In
the 1998 HSB study, only a few percent of the total claims were
attributed to Poor Workmanship or Manufacturer’s Defects. Among the
conditions found were such things as loose or unsupported leads, loose
blocking, poor brazing, inadequate core insulation, inferior short
circuit strength, and foreign objects left in the tank.
Deterioration of Insulation
Insulation
Deterioration was the second leading cause of failure over the past 10
years. The average age of the transformers that failed due to insulation
deterioration was 17.8 years — a far cry from the expected life of 35
to 40 years! In 1983, the average age at failure was 20 years.
Overloading
This
category pertains to those cases where actual Overloading could be
established as the cause of the failure. It includes only those
transformers that experienced a sustained load that exceeded the
nameplate capacity.
Often, the overloading occurs when the plant
or the utility slowly increases the load in small increments over time.
The capacity of the transformer is eventually exceeded, resulting in
excessive temperatures that prematurely ages the insulation. As the
transformer’s paper insulation ages, the strength of the paper is
reduced. Then, forces from an outside fault may cause a deterioration of
the insulation, leading to failure.
Moisture
The
Moisture category includes failures caused by floods, leaky pipes,
leaking roofs, water entering the tanks through leaking bushings or
fittings, and confirmed presence of moisture in the insulating oil.
Inadequate Maintenance
Inadequate
Maintenance was the fourth leading cause of transformer failures. This
category includes disconnected or improperly set controls, loss of
coolant, accumulation of dirt and oil, and corrosion. Inadequate
maintenance has to bear the blame for not discovering incipient troubles
when there was ample time to correct it.
Sabotage and Malicious Mischief
This
category is usually assigned when willful damage was evident.
Surprisingly, there were no reports of transformer damage in the last 10
years due to this cause.
Loose Connections
Loose
Connections could be included in the Maintenance category, but there
was a sufficient number of reports to list it separately. This is
another departure from previous studies. This category includes
workmanship and maintenance in making electrical connections. One
problem is the improper mating of dissimilar metals, although this has
decreased somewhat in recent years. Another problem is improper torquing
of bolted connections.
All Others
This category encompasses all that could not be attributed to the above categories, including "Cause Undetermined."
Summary
A
review indicates that a planned program of maintenance, inspection and
testing would significantly reduce the number of transformer failures,
and the unexpected interruption of power. From a cost standpoint, not
only has the cost of repair increased dramatically, so has the cost of
downtime. Rewinding or rebuilding a large power transformer can take six
to 12 months. A good maintenance program should include the following
recommendations to help achieve maximum service life.
Installation and Operation
- Keep
the electrical loading within the design range of the transformer. In
liquid-cooled transformers, carefully monitor the top oil temperature.
- Install
transformers in locations that are compatible with their design and
construction. If placed outdoors, make sure the unit is rated for
outdoor operation.
- Protect transformers from surges and other external hazards.
Test the Oil
"The
dielectric strength of transformer oil decreases rapidly with the
absorption of moisture. One part water in 10,000 parts oil has been
known to decrease the dielectric strength 50 percent. Oil samples from
each tank, except of course small distribution transformers, should be
given a break-down test at least once each year … so that moisture may
be promptly detected and removed by filtering." (From The Locomotive,
April 1925).
- Gas-in-oil analysis should be performed annually
to measure the dissolved gases in the oil that are created by
developing faults in the transformer. The specific gas and the amount of
gas can identify the type of fault. The fluid screen test should be
performed annually to determine the oil’s ability to perform as an
insulant. These tests include dielectric breakdown, acidity, interfacial
tension, etc.
Additional Maintenance
- Keep the porcelain bushings and insulators clean.
- On
liquid-cooled units, check the radiators for leaks, rust, accumulation
of dirt, and any mechanical damage that would restrict the oil flow.
- Keep electrical connections tight.
- Inspect tap changes on a regular basis. Check the contacts for tightness, burning, pitting, freedom of movement, and alignment.
- The transformer windings, bushings, and arresters should have a Power Factor test on a three-year basis.
- Check
the ground connection on the surge arrester annually. The connection
should be tight, and the lead should be as short as possible. The earth
resistance should be checked during the dry season, and should not
exceed 5 ohms.
- Consider
on-line transformer monitor system for the most critical transformers.
There are a number of on-line systems currently on the market. The
system vendors assemble a variety of probes and sensors, connect them to
a data acquisition unit [DAU] and provide for remote telecommunications
through a modem. The systems also incorporate an "expert system" to
diagnose the problem and distinguish between events that are harmless
and events that are dangerous.